ST. AUGUSTINE, Fla. – As part of an emergency construction contract to replace the County Road 214 overpass beam at I-95 southbound, motorists can expect lane closures and detours in the area throughout the month of January.
On I-95 southbound at CR 214, daily single lane closures are permitted from 8 p.m. to 5 a.m., and double lane closures are permitted from 10 p.m. to 5 a.m. starting Jan. 13.
Motorists can also expect occasional overnight weekend detours of I-95 for demolition, beam, and deck placement. Detours will only be permitted between the hours of 11 p.m. and 5 a.m. Fridays and Saturdays, and the contractor is expected to detour I-95 at most four nights between Jan. 13 and Jan. 29. During these overnight closures, drivers will be detoured via SR 16 eastbound to U.S. 1 southbound to SR 207 southbound to reconnect with I-95 southbound. (see map)
On CR 214, one-lane, two-way traffic over I-95 will be maintained throughout construction. Nightly detours of CR 214 will be permitted between 9 p.m. and 6 a.m.
Stay informed about lane closures and roadwork in your area by following FDOT District 2 at @MyFDOT_NEFL on Twitter or at MyFDOTNEFL on Facebook.